EPCOR Water Main Project

Pages from EPCOR Presentation

EPCOR will be installing over 2 miles of 24” water transmission main pipe along Lincoln Drive in the Town of Paradise Valley.

EPCOR provides water service to nearly 5,000 service connections in Paradise Valley. Currently, water for the area comes from groundwater wells located on the eastern side of service area. This investment in water infrastructure will ensure long-term system reliability and increase capacity in EPCOR’s Paradise Valley water district by nearly 3 million gallons per day by adding a second water source.

Construction began in April of 2019, with completion expected by October of 2019. There will be ongoing traffic restrictions along the Lincoln Drive project limits, from 36th Street to Desert Fairways Drive.


To view additional information and specific schedule, please click here.

Facebook Twitter Email

Other News in Police News

Photograph by Julie Pace

Neighbors App by Ring

Posted on: May 21, 2019
14-1757 Flyer - Michael Gilman Homicide_

Silent Witness Request

Posted on: May 21, 2019
Coffee with a Cop - June 2019

Coffee with a Cop

Posted on: June 11, 2019