Located on the east side of Scottsdale Road between Jackrabbit and Vista, District 30 is the final APS undergrounding project within the Town. APS has nearly completed design of this project and the resident funding threshold has been met. Currently the final easement documentation is being completed. Construction is anticipated to begin in late 2017 with completion in the spring of 2018. If you'd like to be a neighborhood liaison for this project, please contact Jeremy Knapp at 480-348-3622.